The EU has decided that data centres are too important — and too energy-hungry — to remain unmeasured. The recast Energy Efficiency Directive and its delegated regulation created the first mandatory, EU-wide transparency regime for the sector. For operators and investors in Greece, the obligations are already live, and the direction of travel points towards performance standards, not just reporting.

Key Facts — Verified

  • Directive (EU) 2023/1791 (recast Energy Efficiency Directive, Article 12) and Commission Delegated Regulation (EU) 2024/1364 establish the reporting regime.
  • It applies to data centres with an installed IT power demand of at least 500 kW.
  • First reports were due by 15 September 2024; thereafter reporting is annual, by 15 May each year.
  • Reported KPIs include PUE (power usage effectiveness), WUE (water usage effectiveness), ERF (energy reuse factor) and REF (renewable energy factor), alongside surface area, installed power, data volumes and waste heat.
  • Data feeds a European database, publicly available at aggregated (Member State and Union) level, intended to underpin a common EU rating scheme for data centre sustainability.

Who Is Caught — and What Must Be Reported

The 500 kW threshold refers to installed information technology power demand — a level that captures essentially every commercial colocation and hyperscale facility, and many enterprise data centres. Owners and operators must collect and communicate a standardised set of indicators covering energy performance and water footprint: installed power and surface area, energy consumption and its sources, capacity utilisation, waste-heat reuse, water consumption and the four headline ratios (PUE, WUE, ERF, REF).

The mechanics matter: metering and sub-metering must exist at the right boundaries to compute the KPIs defensibly. Facilities designed without adequate metering face genuine retrofit costs — one more reason why compliance belongs in the design phase, a point we develop in our permitting roadmap.

Why This Is Not "Just Reporting"

Three reasons operators should treat the regime as strategic rather than administrative:

  • A rating scheme is coming. The delegated regulation exists explicitly to enable a common Union scheme for rating data centre sustainability. Reported performance will eventually be comparable — and marketable, or not.
  • Minimum performance standards are on the table. The European Commission has commissioned preparatory work on minimum performance standards for EU data centres, and legal commentators widely expect the regulatory framework to tighten further in coming years.
  • Customers and lenders read the same numbers. Hyperscale tenants, ESG-driven investors and financing banks increasingly reference PUE/REF performance in commercial terms and due diligence.

Interaction with the Greek Framework

The EED regime sits alongside national obligations — environmental terms, energy audits under the national implementation of the EED, and, for qualifying entities, the NIS2 cybersecurity framework. For new projects in Greece, the practical approach is to build one compliance architecture from the start: metering design that serves EED KPIs, environmental monitoring that serves the AEPO terms, and documentation that serves both regulators and investors.

What Operators in Greece Should Do Now

  • Confirm whether each facility crosses the 500 kW IT-demand threshold — including planned expansions.
  • Audit metering against the KPI definitions of Regulation 2024/1364 and close measurement gaps.
  • Assign ownership of the annual 15 May reporting cycle and validate data before submission.
  • Track waste-heat reuse feasibility: ERF is likely to attract growing regulatory and commercial attention, and Article 12 EED already pushes waste-heat utilisation.
  • For projects in development, embed the KPIs in the employer's requirements of the EPC contract.

Frequently Asked Questions

Which data centres must report under the EU Energy Efficiency Directive?

Data centres with an installed IT power demand of at least 500 kW must report annually to the European database under Directive (EU) 2023/1791 and Delegated Regulation (EU) 2024/1364. The first reports were due by 15 September 2024, with annual reporting by 15 May thereafter.

Which KPIs must be reported?

The regime covers surface area, installed power, energy consumption, capacity utilisation, waste heat and water consumption, plus the headline ratios: power usage effectiveness (PUE), water usage effectiveness (WUE), energy reuse factor (ERF) and renewable energy factor (REF).

Is the reported data public?

The European database is publicly available at aggregated level — Member State and Union — and is intended to support a common EU scheme for rating the sustainability of data centres.

Sources & Further Reading

  1. Directive (EU) 2023/1791 on energy efficiency (recast), Article 12 — EUR-Lex
  2. Commission Delegated Regulation (EU) 2024/1364 — eur-lex.europa.eu
  3. European Commission, preparatory study on minimum performance standards for EU data centres — energy.ec.europa.eu
  4. White & Case, "Data centres and energy consumption: evolving EU regulatory landscape and outlook for 2026" — whitecase.com

This article provides general information, verified against the cited sources at the date of publication. It does not constitute legal advice.